Edgar Dam

Project Update – June 2024

Update 12 Jun, 2024
June 2024 update

EPBC Decision

The Federal assessment of the project is now complete and it has been determined to be not a controlled action – particular manner. This means that the works must be completed according to the particular manner in the decision notice and no further assessment is required. You can review the referral and associated documentation here.

Quarry

Our final detailed investigation of Sunshine Quarry revealed that it was not suitable. We will progress with a Bridgewater quarry unless the successful contractor puts forward an alternative source that meets our technical and environmental requirements.

Tender

A tender process for the specialist construction services required to complete this work will start in June.